Progress continues to our four acre northern extension despite recent challenging weather conditions. The extension will provide a larger storage area for unsorted and sorted logs, increasing the range and flexibility with which the logs can be cut in mill 1.

The £3m extension includes the construction of a perimeter road and concrete slab for log storage. It will be serviced by a purpose built Sustainable Drainage System (SuDS), including solids and oil interceptors to handle all surface water drainage. The project is expected to be completed by early summer.